Find the cost of sinking a tubewell 280 m deep, having diameter 3 m at the rate of Rs. 3.60 per cubic metre. Find also the cost of cementing its inner curved surface at Rs. 2.50 per square metre.

Open in App
Solution

Depth of well (h) = 280 m Diameter = 3 m Radius(r)=32 m

Volume of earth dugout = πr2 h

=227×32×32×280m3=1980m3

Rate of digging the well = Rs. 3.60 per m3

Cost of digging = Rs. 3.60 × 1980

= Rs. 7128

Area of inner curved surface = 2π rh

=2×227×32×280=2640m2

Rate of plastering = Rs. 2.50 per m2

Cost of plasterin g= Rs. 2.50 × 2640

=Rs. 6600