Find the work done for the force-displacement plot shown below.
Open in App
Solution
Since work done is a scalar product of force and displacement, it can be calculated as area under the force-displacement plot.
So, work done = Area of the triangle = 1/2 x 30 x 4 = 30 x 2= 60 J.