Find the work done in lifting 5 cement bags, each of mass 25kg to the top of a building of height 50m.(consider g=10m/s2)
A
12.5kJ
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
−25kJ
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
62.5kJ
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
−62.5kJ
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C62.5kJ Given, mass of each cement bag (m)=25kg No. of bags =5 ∴ Total mass (M)=nm=5×25=125kg Height of building (h)=50m By the FBD of the combined bags:
Force applied to lift the body (F)=mg Since, applied force and displacement are in the same direction Amount of work done (W)=Fs=mgh =125×10×50 =62500J (or) 62.5kJ