CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project

Activity Duration (days)
1 - 2 2
2 - 3 1
4 - 3 3
1 - 4 3
2 - 5 3
3 - 5 2
4 - 5 4

The critical path (CP) in the network is

A
1-4-3-5
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
1-2-3-5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
1-4-5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
1-2-3-4-5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Join BYJU'S Learning Program
CrossIcon