Question

For a certain loading condition, a saturated clay layer undergoes 40% consolidation in a period of 178 days. What would be the additional time required for further 20% consolidation to occur?

A
89 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
222.5 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
329.5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
400.5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 222.5 days
Time factor, Tv=π4U2for U<60

For same clay layer at different times, t1 and t2 the relationship reduces to

t2t1=(U2U1)2


t2=(6040)2×178

= 400.5 days

Thus additional time needed=t2t1

= 400.5 - 178
= 222.5 days

flag
Suggest Corrections
thumbs-up
3
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Tezarghi's Theory of One-Dimensional Consolidation
SOIL MECHANICS
Watch in App
Join BYJU'S Learning Program
CrossIcon