For a composite steel-beam and RCC-slab floor construction

A
the grade of concrete has to be M20 for the composite action to be satisfactory
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
the longitudinal reinforcement of the slab has to be welded to the beam to develop monollthicity
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
a notch is made in the slab to house the upper flange of the beam
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
shear connectors are provided to develop the composite action
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D shear connectors are provided to develop the composite action
Shear connectors prevent separation between steel girder and in-situ concrete slab by transferring horizontal shear force along contact surface without slip. Thus they are important structural element for composit steel beam and RCC slab floor construction.

flag
Suggest Corrections
thumbs-up
2
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Design of One Way Slab
OTHER
Watch in App
Join BYJU'S Learning Program
CrossIcon