For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively. The expected time is

A
10 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
8 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
9 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
15 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 9 days
Expected time, te=to+4tm+tp6=5+4×8+176=9 days