For a normal RCC work, the slump of concrete should be in the range of ______
Recommended slumps of concrete: | ||
No. | Type of concrete | Slump |
1 | Concrete for road construction |
20 to 40 mm |
2 | Beams and slabs | 50 to 100 mm |
3 | Mass concrete | 25 to 50 mm |
4 | Normal RCC works | 80 to 150 mm |
5 | Impermeable work | 75 to 120 mm |
6 | Concrete to be vibrated | 10 to 20 mm |