Question

For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.

Activity Predecessors Duration (days)
a - 3
b a 4
c a 5
d a 4
e b 2
f d 9
g c, e 6
h f, g 2

If duration of activity f is changed to 10 days, then the critical path for the project is

A
Critical path remains the same and the total duration to complete the project changes to 19 days.
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
Critical path changes and the total duration to complete the project changes to 17 days.
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
Critical path changes but the total duration to complete the project remains the same.
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
Critical path and the total duration to complete the project remains the same.
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is A Critical path remains the same and the total duration to complete the project changes to 19 days.


Critical path adfh=19 days

So, when the duration of activity, f is changed from 9 to 10 days, the critical path remains the same and the project duration will increase to 19 days.

flag
Suggest Corrections
thumbs-up
1