For a project the following data is given.

ActivityDurationEarliestLatest(in days)Start TimeFinish Time1−220111−37071−480112−532143−567143−6107173−747163−747164−668175−7213167−861522

The free float for activity 3-7 is____ (in days)

A
4
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
2
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
3
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 2
From the dat the figure should be constructed,



The activity for 3 - 7, EST = 7

EFT = EST + duration=7+4=11

LFT = 16

LST = LFTDuration=164=12

Total float=LSREST=127=5

Earliest start time of 7 - 8 successor activity = 15

Head event slack=165=1

Free float = total float - head event slack=51=4

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Float and Its Types
OTHER
Watch in App
Join BYJU'S Learning Program
CrossIcon