The correct option is D B-F-J
ActivityDurationEarliestLatestLatestTotalin daysStart TimeFinish TimeStart TimeFinish TimeFloatA200+2=211−2=9119B700+7=77−7=070C800+8=811−8=3113D322+3=514−3=11149E677+6=1314−6=8141F1077+10=1717−10=70G477+4=1116−4=12165H688+6=1417−6=11173I21313+2=1516−2=14161J51717+5=2222−5=17220K61515+6=2122−6=16221
Earliest finish time = Earliest start time + duration
Latest start time = Latest Finish time - Duration
Total float = Latest finish time - Earlist finish time
= Latest start time - Earliest start time
For whichever activity total float is zero that activity is on the critical path from the table we observed that total float is zero for B, F, J.
Hence, the critical path is B-F-J.