For a project the following datais given

ActivityDurationEarliestLatest(in days)StartFinishTimeTimeA2011B707C8011D3214E6714F10717G4716H6817I21316K61522

The critical path is

A
B-E-I-K
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
A-D-I-J
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
C-H-J
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
B-F-J
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D B-F-J
ActivityDurationEarliestLatestLatestTotalin daysStart TimeFinish TimeStart TimeFinish TimeFloatA200+2=2112=9119B700+7=777=070C800+8=8118=3113D322+3=5143=11149E677+6=13146=8141F1077+10=171710=70G477+4=11164=12165H688+6=14176=11173I21313+2=15162=14161J51717+5=22225=17220K61515+6=21226=16221

Earliest finish time = Earliest start time + duration

Latest start time = Latest Finish time - Duration

Total float = Latest finish time - Earlist finish time

= Latest start time - Earliest start time

For whichever activity total float is zero that activity is on the critical path from the table we observed that total float is zero for B, F, J.

Hence, the critical path is B-F-J.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Critical Path and Project Completion Time
OTHER
Watch in App
Join BYJU'S Learning Program
CrossIcon