wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

For concrete exposed to dry conditions, the minimum curing period is:

A
5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
7 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
10 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
14 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 10 days
As per IS 456 : 2000, for any structural concrete member the minimum curing period is 7 days at 90% humidity but if any mineral Admixture is used then it is 10 days.
It is also recommended that the curing duration should not be less than 10 days for concrete exposed to dry and hot conditions and 14 days for concrete with mineral admixture.

flag
Suggest Corrections
thumbs-up
5
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Curing of Concrete
OTHER
Watch in App
Join BYJU'S Learning Program
CrossIcon