For how many months could not a single new application received in that month be completed within that month?
From the table, the months are MAR, MAY, JUN, JUL, AUG, SEPT, OCT, NOV, DEC.. Total =9.
A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men.