(ts)casting=2min;(ts)riser=3min
(ts)casting=k(VA)2
2=k(80×120×202(80×120+120×20+20×80))2
k=0.040138min/nm2
Riser:(ts)riser=k(VA)2
3=0.040138(VA)2
(VA)=8.64
VA=π4d2h2π4d2+πdh
For riser if h = d then VA=d6
d6=8.64
h = d = 51.84 mm