Question
For the network shown above total float is zero for ______ number of activities.
6
Open in App
Solution
The correct option is
A
6
The total float is zero on critical path there are two paths viz.,
1-2-4-7-9 and 1-2-4-8-9
∴
6 numbers.
Suggest Corrections
0
Similar questions
Q.
The network diagram for a project is shown below. The duration of activities is indicated.
The free float for activity 3 - 4 is
Q.
A project consists of 7 activities. The network along with the time duration(in days) for various activities is shown in the figure. The number of Activities whose float is more than 1 day is
Q.
Consider a PERT network as given below:
The expected activity time is as shown in network above. The probability of completion of above project in 24 days is 95%. Calculate the expected activity time for activity 2 - 3, if standard deviation for project is 2.5.
P(%)
90
94
97
z
1.3
1.5
1.8
Q.
For an activity
101
−
201
in AOA network, activity times and duration as shown below. Between total float, interference float, and independent float, which one of the following is the correct sequence in the decreasing magnitude order?
Q.
For activity 2-3, shown in the above figure, calculate the sum of the total float, the free float, and the independent float ....... (day)
( Notations carry usual meaning)
View More
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
Related Videos
Introduction
ACCOUNTANCY
Watch in App
Explore more
Company
Standard XII Accountancy
Join BYJU'S Learning Program
Grade/Exam
1st Grade
2nd Grade
3rd Grade
4th Grade
5th Grade
6th grade
7th grade
8th Grade
9th Grade
10th Grade
11th Grade
12th Grade
Submit
AI Tutor
Textbooks
Question Papers
Install app