For the network shown in the following figure, the time estimates in days for each activity are indicated. Determine the probability ( in %) of completing the project in 36 days. The non exceedance probability (P) for various values of the probability factor Z is as follows. The critical path is shown below.
Z1.01.11.21.3( Pr(%))84.1386.4388.4990.32