Question

For the network shown in the following figure, the time estimates in days for each activity are indicated. Determine the probability ( in %) of completing the project in 36 days. The non exceedance probability (P) for various values of the probability factor Z is as follows. The critical path is shown below.

Z1.01.11.21.3( Pr(%))84.1386.4388.4990.32


Open in App
Solution

tE=t0+4tL+tP6

σ=(tpto6)2

Variance calculation is given in the table below :
Activityt0tmtptEσ21-26-9-181042-44-7-22994-54-10-22119

Critical path = 1 - 2- 4-5

TE=30 days;TS=36 days

Z=TsTEσ

To calculate σ :-

σ2 of critical path

σ2=4+9+9=22

σ=22=4.69

Z=36304.69=1.2793

From the table

Z=1.2793 Probability = 89.94 %

flag
Suggest Corrections
thumbs-up
0
similar_icon
Similar questions
View More
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Probability of Completion of Project
OTHER
Watch in App
Join BYJU'S Learning Program
CrossIcon