Four gardeners with four grass mowers mows 400 square metres of ground in four hours.How long would it take for eight gardeners with eight grass mowers to mow 800 square metres of ground?
A
8 hours
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
6 hours
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
2 hours
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
4 hours
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D4 hours Since 1 Gardner is using one Mower M1×h1w1=M2×h2w2 4×4400=8×h2800 h2=4hrs