Question
Full amount of super-elevation on a horizontal curve is provided at the
A
centre of the transition curve
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
end of the transition curve
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
beginning of the transition curve
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
centre of the circular curve
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B end of the transition curve The full amount of super-elevation is attained by the end of transition curve or at the beginning of circular curve.