G can do a piece of work in 40 days and H can do the same in 10 days. But they were working together and completed the work in 20 days, which of the following can be the reason?
Only H’s efficiency got reduced by 75%
If H’s efficiency reduced by 75%
Work done by H in one day =140
If G and H work together
The work done in one day=140+140=120