Generally to estimate PMP, Pn=42.16D0.475 is used (where Pn= maximum depth of precipitation, D = duration). What are the units of Pn and D respectively in the equation?

A
mm, sec
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
cm, sec
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
mm, hr
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
cm, hr
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D cm, hr
D(duration) is in hours and Pn (maximum depth of precipitation) is obtained in cm.