B
Indicating inventory carrying cost
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
Balance work to complete the project
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
Comparison of actual progress of project with the scheduled progress
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution
The correct option is D Comparison of actual progress of project with the scheduled progress Guntt charts are mainly used for comparison of actual progress of a project with the scheduled progress.