How many workers are required for completing the construction work in 10 days?
1. 20% of the work can be completed by 8 workers in 8 days
2. 20 workers can complete the work in 16 days
3. One-Eighth of the work can be completed by 8 workers in 5 days
Either 1 or 2 or 3
(d) Either statements 1 or 2 or 3 are necessary to answer the question.
1=In 8 days, 8x5= 40 workers are required
Therefore in 10 days = 40x8/10 = 32 workers are required
2= Required no. of workers = 20(16/10) =32
3=In 5 days 8x8= 64 workers
Therefore in 10 days 64x5/10=32 workers