How much work is done in moving a charge of 10 C across two points having a potential difference 24 V?

Open in App
Solution

The amount of charge Q, that flows between two points at potential difference V (= 24 V) is 10 C. Thus, the amount of work W, done in moving the charge is
W = V × Q
= 24 V × 10 C
= 240 J.