If 10 men take 30 days to complete a work, how many days would 15 men take to finish the work?

A
30
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
45
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
60
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
20
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses