If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, the number of chairs made by 18 carpenters in 360 days each working 8 hours a day will be:
A
1380
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
1320
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
1260
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
920
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A1380 12 carpenters working 6 hours a day can make 460 chairs in 240 days.
⇒12×240×6 hours of work can make 460 chairs.
Let 18 carpenters working 8 hours a day can make n chairs in 36 days.
⇒18×360×8 hours of work can make n chairs.
Since, number of working hours is directly proportional to the number of chairs that can be made,