If 12men or 18 women can complete a piece of work in 7 days , then in how many days can 4 men and 8 women complete the same work ?
A
9 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
12 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
6 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
7 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is A9 days 12 men =18women 2 men =3 women 12 men or 18 women can complete a piece of work in 7 days. 4 men and 8 women =6+8 women =14 women. If 18 women can complete a piece of work in 7 days. So, 1 women can complete a piece of work in 7×18 days. So, 14 women can complete a piece of work in 7×1814 days =9 days.