The correct option is A 24
Given,
In 2 days, 12 typists can type a number of pages.
We know that if the time allowed is less, then the number of typists required is more.
So, Number of days(x)∝1Number of typists(y)
∴x1x2 = y2y1
Given,
x1 = 2 days
y1 = 12 typists
x2 = 1 day
and y2 = Number of typists required
⇒ y2 = x1 × y1x2
⇒ y2 = 2 × 121 = 24
Therefore, the number of typists required is 24.