Question

If 15 men can complete work in 30 days, then how much time will it take for 10 men?

A
25 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
35 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
45 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
55 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 45 days

If more men are available to work, then it will take less days.

So, M1D

M1D1=M2D2

Given values:

M1=15,D1=30days,M2=10,D2=?

Putting in the values,

15×30=10×D2

D2=45days

<!--td {border: 1px solid #ccc;}br {mso-data-placement:same-cell;}-->

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Percentages and Why Percentages
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon