If 15 men can finish a job in 48 hours, how many men will be required to do the same job in 30 hours. [1 MARK]
Concept: 1 Mark
As the number of men increases, the time required to finish the job decreases.
Men×time=constant
Let "m" be the number of men required.
15×48=m×30
m = 24