Question

If 16 workers can do a work in 20 hours then how many workers can do the work in 10 hours?

A
8
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
16
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
32
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
24
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 32
This question is based on Inverse proprtion
According to the given conditions,
No. of workers Time taken
16 20 hours
x 10 hours
By inversion proportion,
16×20=x×10
x=16×2010
x=32
Answer is 32 workers

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon