CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

If 18 pumps can raise 2170 tonnes of water in 10 days working 7 hours a day then in how many days will 16 pumps raise 1736 tonnes of water working 9 hours a day

A
6
No worries! Weā€˜ve got your back. Try BYJUā€˜S free classes today!
B
7
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
8
No worries! Weā€˜ve got your back. Try BYJUā€˜S free classes today!
D
9
No worries! Weā€˜ve got your back. Try BYJUā€˜S free classes today!
Open in App
Solution

The correct option is B 7
18 pumps raise 2170 tonnes in 10 days working 7 hours a day.

In 1 day they raise 217010=217 tonnes

In 1 hour they raise 2177=31 tonnes.

1 pump raises water =3118 tonnes.

Now,

16 pumps will raise =3118×16 tonnes.

Working 9 hrs a day they will raise =3118×16×9 tonnes

Let the number of days be d days.

Thus total =3118×16×9×d

1736=3118×16×9×d

d=1736×189×16×31=7 days.


flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon