wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

If 20 men working 8 hours per day can complete a piece of work in 21 days. How many hours per day must 48 men work to complete the same job in 7 days

A
12
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
20
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
10
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
15
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is C 10
We know, Work = Men × hr/day×days

Work is same in both cases

Let 48 men will complete the same work in x hr/day

20×8 hr/day ×21=48×x hr/day ×7

48x=(20×8×21)7

48x=20×8×3

x=(20×8×3)48

x=48048

x=10

48 men must work 10 hr/day to complete the same work in 7 days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon