If 3 men or 6 boys can finish a work in 20 days , then how long will 4 men and 12 boys take to finish the same work ?
A
2 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
4 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
6 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
8 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B6 days 3 men =6 boys So, 1 man =2 boys 3 men or 6 boys can finish a work in 20 days. 4 men and 12 boys =4+6 men =10 men. 3 men can finish a work in 20 days. 10 men can finish the work in 20×310=6 days.