Days | Hours | Men |
15 | 12 | 32 |
24 | 10 | x |
Let
P1 = 32
P2 = x
H1 = 12
H2 = 10
D1 = 15
D2 = 24
W1 = 1
W2 = 1
(2 mark)
Now apply the formula method, (P1×D1×H1)/W1 =(P2×D2×H2)/W2 (1 mark)
⇒(31×15×12)/1=(x×24×10)/1
x=24
To complete the same work 24 men needed.
To complete double the work 24 × 2 = 48 men are required.
(1 mark)