wiz-icon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

If 35 men can do a piece of work in 30 days, in how many days will 21 men can do it?

Open in App
Solution

Let the required number of days be x. We know that the number of days is inversely proportional to the number of men working. Thus x=k21, where k is the constant of proportionality. We also know that 30=k35 from the given data. Hence k=35×30. We obtain
x=35×3021=50.
Hence 21 men need 50 days to complete the work.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Adaptive Q2
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon