CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

If 36 men can do a piece of work in 25 days, in how many days will 15 men complete the same work?

Open in App
Solution

If 36 men can do the work
In 25 days, 1 man could do
it in 25×36 days
1 man can do 125×36th of the
work in 1 day
15 man could do (1525×36)th
of the work in 1 day
It would take 25×3615=60
days for them to complete
the work

flag
Suggest Corrections
thumbs-up
1
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Time and Work
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon