If 36 men can do a piece of work in 25 days, in how many day will 15 men do it?
Here less men, more days.
∴ Let in x days, 15 men can finish the work
Therefore,
Men3615Days25x
By inverse variation
36:15=x:25
3615=x25⇒15×x=36×25⇒x=36×2515=60
∴ The work will be finished in 60 days