If 39 men can dig a canal in 15 days, in how many days can 45 men dig a canal whose length is double this canal?
175 men can dig a canal 3150 m long in 36 days. How many men are required to dig a canal 3900 m long in 24 days?
A contractor undertakes to dig a canal, 6 kilometers long, in 35 days and employed 90 men. He finds that after 20 days only 2 km of the canal have been completed. How many more men must be employed to finish the work in time?