If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?
(a) 52
(b) 31
(c) 13
(d) 65

Open in App
Solution

(a) 52
Number of men required to finish the work in 26 days = 40
Number of men required to finish it in 1 day = 40 × 26 = 1040 men (More men means less days)
Number of men required to finish it in 20 days = 1040 = 52
20