The correct option is D 6 men
Given,
5 men can do a piece of work in 6 days.
Number of days given = 5 days.
We know that if the time is less, then the number of men required to finish a work will be more.
Number of men(x)∝1Number of days(y)
∴x1x2 = y2y1
Let,
x1 = 5 men
y1 = 6 days
y2 = 5 days
and, x2 = Number of men required
⇒5x2 = 56
⇒x2 = 5×65 = 6 men