If 5 men can do a piece of work in 6 days, then how many men will finish the same work in 5 days?

A
5 men
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
4 men
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
8 men
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
6 men
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 6 men
Given,
5 men can do a piece of work in 6 days.
Number of days given = 5 days.

We know that if the time is less, then the number of men required to finish a work will be more.
Number of men(x)1Number of days(y)
x1x2 = y2y1

Let,
x1 = 5 men
y1 = 6 days
y2 = 5 days
and, x2 = Number of men required

5x2 = 56
x2 = 5×65 = 6 men

flag
Suggest Corrections
thumbs-up
3
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon