If 5 men can paint a wall 100 metres long in 10 days of a 8 hours each. In how many days of 6 hours each will 8men paint a wall 30 metres long?
A
10
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
2.5
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
1.5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B2.5 Total hours in 10 days =10×8=80 hours Total man-hours needed for paint 100 m wall =5×8=40 man-hours. Man-hours needed for 1 meter wall painting=400/100=4 man-hour. Now, 30×4=120 m-h to do 30 meters. 120 m-h/8 men =15 hours 15 hr/6 hr/day =2.5 days.