Question

If 5 men can paint a wall 100 metres long in 10 days of a 8 hours each. In how many days of 6 hours each will 8men paint a wall 30 metres long?

A
10
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
2.5
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
1.5
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution

The correct option is B 2.5
Total hours in 10 days =10×8=80 hours
Total man-hours needed for paint 100 m wall =5×8=40 man-hours.
Man-hours needed for 1 meter wall painting=400/100=4 man-hour.
Now,
30×4=120 m-h to do 30 meters.
120 m-h/8 men = 15 hours
15 hr/6 hr/day =2.5 days.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Introduction to Direct Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon