If 6 men and 8 boys can do a piece of work in 10 days and 26 men and 48 boys can do same in 2 days, the time taken by 15 men and 20 boys to do the same type of work will be :
A
5 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
4 days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
6 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
7 days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B4 days Let 1 man's 1 day's work =x and 1 boy's 1 day's work =y. Then, 6x+8y=110 and 26x+4812
Solving these two equation, we get : x=1100 and y=1200 (15 men +20 boy)'s 1 day's work =(15100+20200)=14 So, 15 men and 20 boys can do the work in 4 days.