CameraIcon
CameraIcon
SearchIcon
MyQuestionIcon
MyQuestionIcon
1
You visited us 1 times! Enjoying our articles? Unlock Full Access!
Question

If 7 men or 9 women can do a piece of work in 32 days, in what time 7 men and 9 women will complete 12 of the work?

Open in App
Solution

Since
7 Men = 9 Women
7 men and 9 women = 14 men = 18 women
Now,
Men Work done Time (days)
7 1 32
14 1/2 x
x32=714×1/21
=714×12×32=8days

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Inverse Proportions
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon