If 70 men dig 15,000 sq.m of a field in 5 days, how many men will dig 22,500 sq.m field in 25 days?

A
12 men
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
18 men
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
15 men
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
21 men
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
Open in App
Solution

The correct option is D 21 men
Given, 70 men dig 15000 sq.m in 5 days
70×5=15000

To dig the 22500 sq.m in 25 days.

Let x men are required,
x×25=22500
Men required 70×5x×25=1500022500

x=70×5×2250025×15000=21 men.

flag
Suggest Corrections
thumbs-up
0
Join BYJU'S Learning Program
similar_icon
Related Videos
thumbnail
lock
Adaptive Q2
MATHEMATICS
Watch in App
Join BYJU'S Learning Program
CrossIcon