If 80 people can finish a work within 16 days by labouring 6 hours a day. Then how many hours per day should 64 people work to complete that job within 15 days?
A
10 hours
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
15 hours
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
8 hours
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
D
5 hours
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C 8 hours Let the number of hours required be x. Number of person No. of days No. of hours 80 16 6 64 15 x ∴80×16×6=64×15×x ⇒x=80×16×664×15=8hours ∴ 64 people can complete that job within 15 days if they work 8 hours per day.