if A completes a piece of work in 3 days , which 'B' completes it in 5 days and 'C' takes 10 days to complete same work .how long will they take to complete the work,if they work together?
A
3019days
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
B
3017days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
C
4019days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
4017days
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is D3019days
A completes work in 3 days.
B in 5 days.
C in 10 days.
Together, their work per day = 13+15+110=1930
Therefore, time taken to complete whole work together = 3019=days