If Machine X can produce 1,000 bolts in 4 hours and Machine Y can produce 1,000 bolts in 5 hours, in how many hours can Machines X and Y, working together at these constant rates, produce 1,000 bolts?
A
329 hours
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
229hours
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
129hours
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
334hours
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is C229hours Machine X can produce 100 bolts in 4 hrs.
So, it can produce 10004=250 bolts in an hour.
Machine Y can produce 1000 bolts in 5 hrs.
So, it can produce 10005=200 bolts in an hour.
So, together they can produce 250+200=450 bolts in an hour.
So, they will produce 1000 bolts in 1000450=229 hours. Option B