If P is the standard consistency of the given cement sample, then quantity of water to be added to prepare a cement paste for determining the initial setting time is
A
(P/4 + 3) % of weight of cement
No worries! We‘ve got your back. Try BYJU‘S free classes today!
B
0.85 P % of weight of cement
Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses
C
P % of weight of cement
No worries! We‘ve got your back. Try BYJU‘S free classes today!
D
0.78 P % of weight of cement
No worries! We‘ve got your back. Try BYJU‘S free classes today!
Open in App
Solution
The correct option is B 0.85 P % of weight of cement The time elapsed between the moment that the water is added to the cement, to the time that the paste starts losing its plasticity. 300 gm of cement is taken and made a cement paste of consistency 0.85 P. When the needle penetrates only to a depth of 33 to 35 mm from the top (5 to 7mm from bottom), the test is completed