If P, Q and R can do a work in 30, 90 and 45 days respectively. In how many days can P complete the work if Q and R help P every third day?
23
Work done by P in one day = 130
Work done by Q in one day = 190
Work done by R in one day = 145
Work done in 3 days = 190+145+330=215
In 21 days, 1415 of the work will be completed.
Remaining 115 work will be completed by P in 2 days.
Total work will be completed in 23 days.